The short answer. If you buy a building plot in Mallorca, an “approved project” is not enough to establish permission to build. Ask for the municipal licence, the authorised drawings, the execution-project status and the remaining deadlines. A basic project can support a licence application but cannot authorise construction by itself; an application awaiting a decision is not a granted licence.
Planning a personal villa means establishing exactly what can be delivered. Balearic Blue's live Son Vida and Son Gual listings illustrate the documents to check before signing; their descriptions are not parcel-specific planning opinions.

What does an approved villa project in Mallorca actually mean?
The useful question is not simply “Is it approved?” It is “Approved by whom, for which parcel, on which drawings, and subject to which conditions?” Under the Balearic Urban Planning Law, known as LUIB, a new villa requires municipal urban-planning authorisation. An architectural design is not that authorisation.
A professional endorsement of drawings is also different from a municipal grant. If “project approved” means the town hall has approved it, request the actual resolution and its attachments. If it means only that the architect has completed the design, the purchase has a different planning status.
The licence stages, in plain English
| Stage or description | What it means | What the buyer needs to see |
|---|---|---|
| Basic project — proyecto básico | Defines the general characteristics and proposed performance of the villa; sufficient to seek a licence, insufficient to start construction. | The drawings and planning statement, with the parcel clearly identified. |
| Execution project — proyecto de ejecución | Develops the basic project into the full technical definition of the work, including details, materials, systems and equipment. | The complete technical project and evidence of its municipal status; it is not a substitute for a licence. |
| Licence applied for | An application has been submitted; permission has not necessarily been granted. | The submission receipt, complete application and current file status. |
| Licence granted on a basic project | Municipal authorisation exists, but the matching execution project and commencement requirements still matter. | The grant, conditions, execution-project submission and conformity position. |
| Licence granted with an execution project | The detailed project forms part of the authorised file. | The valid grant, authorised project, conditions, appointments and remaining periods. |
These are practical distinctions, not a separate statutory classification. The execution project can accompany the basic project or follow later. It cannot reduce declared performance or alter the licensed uses and conditions. The definitions follow LUIB and the Technical Building Code.
Our Mallorca buying guide covers the wider purchase sequence; the municipal file needs its own technical review.
What do the Son Vida and Son Gual listings tell us?
The current listings provide the following facts. “Project constructed area” is the constructed area each listing states for the proposed villa; it is not living area, a confirmed planning allowance or a completed building measurement. Bedrooms refer to the planned villa, and prices are asking prices for the listed plot-and-project offering.
| Reference | Area | Plot m² | Project constructed area m² | Bedrooms | Asking price |
|---|---|---|---|---|---|
| PRJ0015 | Son Vida | 3,274 | 937 | 6 | €1,350,000 |
| PRJ0016 | Son Vida | 2,366 | 784 | 6 | €1,250,000 |
| PRJ0017 | Son Vida | 2,163 | 741 | 5 | €1,250,000 |
| PRJ0012 | Son Gual | 7,728 | 570 | 4 | €1,750,000 |
Son Vida: a licence claim to verify, not ignore
PRJ0015 and PRJ0017 state that an approved municipal building licence is included. PRJ0016 includes the plot, complete architectural project and municipal building licence. All describe construction as able to begin immediately.
For each, obtain the grant, establish whether it rests on a basic or combined project, check conditions and calculate the time remaining. The listings do not state grant dates, execution-project submissions or licence resolutions.
Our Son Vida area guide can help with the residential choice. It cannot establish the lawful building envelope of a particular parcel.
Son Gual: project information without a confirmed licence status
PRJ0012 is described as a plot with a luxury villa project. Its supplied description does not state that a municipal building licence has been granted. Do not infer approval from the project images, bedroom count or proposed constructed area. Request the application or grant documents and establish the actual stage before comparing it with the Son Vida offerings.
Parcel-specific buildability for every listed plot is not confirmed by this article. It must be verified with the competent town hall and an architect. Neither the plot size nor the project size in the table establishes a permitted development ratio. The images here are developer visualisations of proposed homes, not photographs of completed villas.

Does a licence application become approved if the council does not reply?
Not for a new villa. LUIB sets a three-month decision and notification period from a complete application, subject to lawful suspensions and exceptions. That is a procedural period, not a guaranteed delivery date.
New-building works require express authorisation and are subject to negative administrative silence under national law. An unanswered application does not become permission to construct the villa merely because the decision period has passed.
Palma's general licence procedure page describes positive silence, with limitations. It should not be read as automatic approval for new-building works. The national rule for those works is the important distinction; see the Land and Urban Rehabilitation Act.
For an offering described as “licence applied for”, ask your lawyer and architect to inspect the complete file, including requests for further information. A receipt proves submission. It does not prove that the application is complete, compliant or granted.
How long do you have to start and finish building?
The licence and applicable plan come first
The licence must state the commencement and completion periods in accordance with the general plan. Only where the general plan does not fix them do the LUIB fallback periods apply: six months to start and three years to finish.
These are not universal Palma deadlines. A current neighbourhood-wide commencement or completion period for Son Vida or Son Gual is not confirmed in the research. Read the actual grant and applicable planning rather than inserting the fallback into your purchase timetable.
The periods run from notification of the licence or, where relevant, from expiry of the one-month execution-project verification period. The current LUIB provisions distinguish these clocks.
A basic-project licence has a separate deadline
When a licence is granted on a basic project, the matching execution project must be submitted within nine months of grant. Failure extinguishes the licence's effects by operation of law and requires a new licence.
The municipality has one month to check conformity. After that month without a contrary notification, works may start subject to all other requirements. This is not the same as positive silence on the original new-villa application. LUIB also requires at least ten days' advance notice to the municipality before commencement.
For the Son Vida plots, ask for documentary evidence of the execution-project position rather than assuming “complete architectural project” answers that question.
Buying the plot does not restart the clock
Works licences are transferable, but the old and new holders must communicate the transfer in writing to the municipality. Without that communication, both remain subject to the resulting holder responsibilities. The sale does not reset the licence deadlines.
A justified extension application submitted before expiry can secure an extension equal to half the relevant original period. Further completion extensions are conditional, not automatic. Failure to start or complete within the applicable periods can lead to municipal lapse proceedings; a lapsed licence cannot authorise work to begin or continue. Ask for the history of notifications and extensions, not just the original grant.
What are ICIO and municipal building-licence fees?
Keep acquisition taxes separate from construction charges. ICIO — Impuesto sobre Construcciones, Instalaciones y Obras — is not charged on the plot purchase price. Its base is the real and effective material-execution cost of the work, excluding VAT, associated municipal taxes and fees, professional fees, contractor's business profit and other non-material-execution items.
Palma's ICIO rate is 4%. Calvià's is also 4%, but that does not make the municipalities' entire fee schedules interchangeable.
Why Palma's rates should not simply be added
For new buildings, Palma's urban-planning service fee is 2.61% of the total real and effective work or installation cost. It is a separate tasa, not ICIO.
Palma then deducts 50% of the urban-planning service fee paid in the same file from the gross ICIO charge, before applying ICIO bonifications. The deduction applies once, to the initially declared amounts.
Consequently, simply adding 4% and 2.61% misstates the combined charge. The bases may differ, and additional charges or final adjustments require the actual municipal calculation. Request the assessments and receipts, and agree how outstanding amounts will be handled on purchase. The Palma fiscal ordinances and Calvià fiscal ordinances are the relevant municipal sources.
Is buying a plot taxed like buying a completed new villa?
No. A building plot sold within a business or professional activity is subject to 21% VAT, not the 10% completed-housing rate. A design for a future residence does not turn bare land into a completed dwelling.
A genuine private sale outside an economic activity is generally subject to ITP instead. “Individual seller” is not enough to decide this: someone who urbanises land or promotes for sale may be a VAT entrepreneur even occasionally.
The general Balearic ITP scale is progressive: 8% on the first €400,000; 9% from €400,000 to €600,000; 10% from €600,000 to €1 million; 12% from €1 million to €2 million; and 13% above €2 million. Each marginal band applies only to its own portion, not the entire price.
For a notarised, registrable purchase subject to VAT rather than ITP, variable AJD generally applies. The general Balearic rate is 1.5%, with 2% applying to the specified property-transfer deeds where the statutory real or declared value is at least €1 million. Confirm the taxable base and transaction structure rather than applying a rate to a listing label.
None of the supplied listings confirms the seller's tax status or the transaction's final tax treatment. Our purchase-cost guide gives wider context; request transaction-specific advice through fiscal advisory before agreeing a binding budget.

Do you need decennial insurance when building your own villa?
The residential-building regime normally requires a ten-year structural guarantee, commonly called seguro decenal. It covers damage to specified structural elements compromising mechanical resistance or stability, not every finish or installation.
There is a narrow self-promoter exception: an individual self-promoter of a single single-family dwelling for their own use need not provide the guarantee initially. It is not a blanket exemption for every owner commissioning construction.
If that dwelling is transferred during the ten-year period, the promoter normally must provide cover for the remaining period. Dispensation requires proof of personal use and the buyer's express release of the promoter, as addressed by the notary and registry. Decide the guarantee position with your advisers before construction, including how it would affect a later sale. The governing source is the Building Act, LOE.
What permission allows you to occupy the finished villa?
A final works certificate is not itself an occupation licence. The certificate is signed by the works director and execution director; the completion documentation also forms part of the Libro del Edificio, the building's authorised-project and use-and-maintenance record.
The municipal occupation or first-use licence checks compliance with the works licence and authorised project and permits use. Under the reformed Balearic system, it replaces the first-occupation cédula and also recognises habitability.
This does not mean all habitability cédulas were abolished. Earlier applications and licences can require transitional treatment, and renewal remains relevant. The corresponding renewal cédula must be requested ten years after the occupation or first-use licence. Your architect and lawyer should identify the correct completion route for the file, rather than relying on an older checklist requiring separate first-occupation approvals in every case.
A building licence also does not establish eligibility for tourist letting. Treat that as a separate enquiry using our holiday-rental licence guide, not as an assumed benefit of a new villa.
What should you check before signing for a plot with a project?
Bring your lawyer and architect into the same document review. Our broader property due-diligence checklist complements these plot-specific checks.
- Identity and title: obtain a current nota simple, confirm the registered owner, rights and charges, and match the finca with Catastro and the physical survey. An informational extract is not conclusive registry certification or proof of buildability.
- Current planning: obtain municipal planning information and have the architect verify use, buildability, occupation, height, storeys, setbacks and applicable constraints. Palma offers a planning-consultation or urban-development certificate; a map alone is not enough.
- Licence evidence: inspect the actual municipal grant and authorised drawings, or establish clearly that only an application exists.
- Execution-project position: identify the submitted version, conformity status, conditions and required professional appointments.
- Time remaining: review notification dates, commencement evidence and extensions, then confirm the transfer communication and a viable timetable.
- Money and liabilities: confirm seller tax status, purchase-tax bases, municipal assessments, receipts and outstanding construction-related charges.
- Completion and guarantee route: establish the decennial-guarantee position, final works documentation and occupation or first-use requirements.
- Contract scope: have advisers record exactly which land, project documents and licence position you are buying, and how unresolved checks affect your commitment.
You can compare plots for sale in Mallorca or set up property alerts while the document review proceeds. To discuss a particular reference, contact a Balearic Blue advisor. The right next step is a clearly identified file, not an assumption based on the word “approved”.
Does an approved project mean I can start building immediately?
Not necessarily: a basic project is insufficient to start construction. Obtain the municipal licence and verify the execution-project status, conditions, commencement requirements and remaining periods.
Can an unanswered building-licence application become permission for a new villa?
No: new-building works require express authorisation and are subject to negative administrative silence. The application decision period is not automatic permission to build.
Are six months to start and three years to finish universal Mallorca deadlines?
No: those are LUIB fallback periods only where the general plan does not fix them. Check the actual licence; a licence on a basic project separately requires the execution project within nine months of grant.
Do Palma's ICIO and licence-fee rates simply add together?
No: Palma charges 4% ICIO and a 2.61% new-building service fee, but deducts 50% of the fee paid in the same file from gross ICIO before bonifications. Obtain the municipal calculation because bases and final adjustments matter.
Is Son Gual PRJ0012 confirmed as licensed in this guide?
No: the supplied listing describes a villa project but does not confirm a granted municipal building licence. Parcel-specific buildability for it and the Son Vida plots must be verified with the town hall and an architect.
Is the final works certificate enough to move into the villa?
No: completion certification is distinct from municipal occupation or first-use permission. Under the reformed Balearic system, that licence replaces the first-occupation cédula, subject to transitional treatment for older files.
Sources checked on 10 November 2026: BOE (LUIB, Technical Building Code, Land and Urban Rehabilitation Act, Local Corporations Services Regulation, Local Finance Act, LOE, VAT and transfer-tax legislation, and Balearic occupation reform); Ajuntament de Palma (licensing, planning information and fiscal ordinances); Ajuntament de Calvià (ICIO and fiscal ordinances); ATIB (ITP and AJD); AEAT (VAT rates); Colegio de Registradores and Dirección General del Catastro (property identification and records); Balearic Blue (live listing data and developer visualisations). This is general information, not legal or tax advice; obtain independent transaction-specific advice before committing.